Archive for July 12th, 2009

Sat., 7/18 end of day

July 12th, 2009 lynnep 1 comment

Update 7/20/09 8:14am: Forgot to mention that the porch concrete forms did not get done so that will be a priority task for this  Thursday I’m sure.

7/19/09: I stopped by after church today and took some pictures of yesterday’s work. More great progress it appears. The luan was laid in the kitchen and bathroom so linoleum can go in next Thursday. Laminate will follow Friday and Saturday I’m sure. Siding is done at rear and on the west side, mostly done on the east side and well underway on the front. I forgot to check and see if the basement egress window was installed or if the plywood was still up. Kitchen cabinets were also unpacked and are ready to go back in place when the kitchen floor is down. That could happen with volunteers next Saturday (maybe)  or Andy and Bill may have them installed. We have a man who makes all our countertops (super cheap) and will install the cabinets himself for no additional money. Sometimes we go that route, sometimes not. Andy will make that call. If they aren’t installed by Saturday, I bet he will have it done by this guy (forget his name – Sorry!)

Enjoy the pictures!

Front view Sat. afternoon

Front view Sat. afternoon

Bathroom floor luan

Bathroom floor luan

Kitchen floor luan

Kitchen floor luan

Kitchen cabinets unpacked, now in LR corner